Project Name: SBDE Ft Bragg
Customer: Army Corp of Engineers
Location: Fort Bragg, NC
Size: (2) 4,800 Square Feet
Project Start Date: 2/13/2008
Actual Date Completed: 09/24/2008
Days to Complete: 222
Description: ECHO DCL delivered the complete design and construction of (5) two story permanent modular Administration Buildings for a total of 30,000 square feet at Ft. Bragg, NC. Scope of work included design, engineer, and manufacturing. Complete turnkey construction included delivery, set-up, foundation, pit set at grade, steps, decks, sprinkler, fire alarms, pitched roof system, brick exterior and Data/Commutation system. Upgraded Electrical drops in the floor and ceiling are installed to handle a multitude of Computers and Servers. An ECHO DCL Superintendent was present from Start to Finish.