Project Name: 917th Admin Building
Customer: US Air Force
Location: Barksdale, AFB LA
Size: 3,360 Square Feet
Contract Start Date: 07/21/2009
Actual Date Completed: 08/20/2009
Days to Complete: 30
Description: ECHO DCL delivered the complete Design and construction of two modular buildings To Barksdale AFB to serve as the new modular office space for the Flight Squadron. SOW included designing, engineering, and manufacturing. Complete turnkey construction included delivery, set-up, steps, canopy, water, sewer and electrical. An ECHO DCL Superintendent was present from start to finish.