Customer Name:
|
John J. Kirlin Special Projects |
---|---|
Name/Title:
|
Chris Phillips – Quality Assurance |
Address:
|
1585 3rd Street |
Fort Polk, LA 71459 | |
Project Name:
|
Modular PT/OT Clinic |
Contract Number:
|
77014-12 |
Prime Contractor:
|
ECHO DCL, Inc. |
Contract Type:
|
FFP |
1. Contract Date:
|
February 14, 2011 |
2. Mobilization Date:
|
May 31, 2011 |
3. Completion Date:
|
June 8, 2011 |
5. Location:
|
Fort Polk, LA |
ECHO DCL completed the design and construction of one modular PT/OT Facility for a total of 11,045 square feet. Scope of work included design, engineering, and manufacturing. Complete turnkey construction included delivery, set-up, fire alarm/mass notification, nurse call, fire sprinkler, building communications, building water, sewer and electric, gutters, downspouts, awnings, decks, steps and ramps. An ECHO DCL Superintendent was present for 42 days from Start to Finish.