Border Modular Patrol Station

Modular Patrol Station
Modular Patrol Station

 Modular Patrol Station

Customer Name:
Fort Worth District USACE
Name/Title:
Robin Prince USACE, Contracting Specialist
Address:
819 Taylor St
Rm 2A19
Texas 76102
Project Name:
Border Patrol Station
Contract Number:
W9126G-10-T-0205
Prime Contractor:
ECHO DCL, Inc.
Contract Type:
FFP
1. Contract Date:
May 17, 2011
2. Mobilization Date:
July 29, 2011
3. Completion Date:
September 19, 2011
5. Location:
Sonoita, Arizona

ECHO DCL completed the design and construction of one Modular Patrol Station for a total of 6,353 square feet.  Scope of work included design, engineering, and manufacturing. Complete turnkey construction included foundation, delivery, set-up, fire alarm/mass notification, fire sprinkler system to meet NFPA 13 and UFC, interior building communications, complete security system,  site and building water, fire water, sewer and electric, gutters, awnings, decks, steps and ramps.  This project included a small workout room for the Border Patrol agents.  ECHO DCL was on-site from mobilization to the completion of all work. An ECHO DCL Superintendent was present from Start to Finish.  Project was complete on time.