Project Name: Navy/Marine Intel Training Facility
Customer: Navy/Marine Intel Training
Location: Virginia Beach, VA
Size: 3,840 Square Feet
Contract Start Date: 01/05/2006
Actual Date Completed: 09/27/2006
Days to Complete: 264
Description: ECHO DCL delivered the complete design and construction of a 3,840 square foot permanent modular Marine Intel Training Facility Building and Computer/Business Office. Scope of work included design, engineer, and manufacturing. Complete turn- key construction included delivery, set-up, foundation, steps, decks, ramps, and bricked on site. All electrical, water, sewer, and fire alarm hook-ups. An ECHO DCL Superintendent was present from Start to Finish. Project was completed on schedule.