Modular Medical Building
ECHO DCL has been awarded a contract for one modular embedded health clinic at Fort Benning. This modular health clinic is approximately 5000 square feet. Scope of work included design, engineering, and manufacturing. Complete turnkey construction included delivery, set-up, fire alarm/mass notification, duress, building communications, site and building water, sewer and electric, sidewalks, awnings, decks, steps and ramps. This building serves as the new clinic space for the soldiers of Fort Benning. An ECHO DCL Superintendent is present from Start to Finish.
Customer Name: Martin Army Community Hospital
Project Name: Fort Benning EBH
Contract Number: W912DY-12C-0010
Prime Contractor: ECHO DCL, Inc.
Contract Type: FFP
1. Contract Date: September 29, 2012
2. Mobilization Date: November 26, 2012
3. Completion Date: March 22, 2013
5. Location: Fort Benning, GA