Customer Name: | Ft. Myer |
---|---|
Name/Title: | Ken Mitchell / Contracting Officer |
Address: | Building 400 |
Fort Myer, VA | |
Project Name: | Fort Myer Band Hall/Locker Room |
Contract Number: | W91QF7-10-C-0046 |
Prime Contractor: | ECHO DCL, Inc. |
Contract Type: | FFP |
1. Contract Date: | January 18, 2011 |
2. Mobilization Date: | March 1, 2011 |
3. Completion Date: | March 17, 2011 |
5. Location: | Fort Myer, VA |
ECHO DCL completed the design and construction of one modular Band Hall Facility for a total of 2138 square feet. Scope of work included design, engineering, and manufacturing. Complete turnkey construction included delivery, set-up, fire alarm/mass notification, electric, sidewalks, and gutters. An ECHO DCL Superintendent was present from Start to Finish.