Customer Name: | Kialegee Tribal Town |
---|---|
Name/Title: | Sheila Harjo, Program Director |
Address: | PO Box 332 |
Wetumka, OK | |
Project Name: | Kialagee Tribe |
Contract Number: | 11116 |
Prime Contractor: | ECHO DCL, Inc. |
Contract Type: | FFP |
1. Contract Date: | June 4, 2010 |
2. Mobilization Date: | July 20, 2012 |
3. Completion Date: | August 17, 2012 |
5. Location: |
ECHO DCL completed the design and construction of one modular Administration Facility for a total of 3525 square feet. Scope of work included design, engineering, and manufacturing. Complete turnkey construction included delivery, set-up, site and building water, sewer and electric, awnings, decks, steps and ramps. An ECHO DCL Superintendent was present from Start to Finish.