Customer Name:
|
USPFO For Tennessee |
---|---|
Name/Title:
|
Major Andrew Milligan |
Address:
|
NG Armory |
3041 Sidco Drive | |
Nashville, TN 37204 | |
Phone:
|
|
Fax:
|
|
Email:
|
|
Project Name:
|
Modular Barracks |
Contract Number:
|
W91217-10-C-0008 |
Prime Contractor:
|
ECHO DCL, Inc. |
Contract Type:
|
FFP |
1. Contract Date:
|
June 24, 2010 |
2. Mobilization Date:
|
August 17, 2010 |
3. Completion Date:
|
December 10, 2010 |
5. Location:
|
Catousa, GA |
ECHO DCL completed the design and construction of four modular barrack buildings for a total of 22,880 square feet. Scope of work included design, engineering, and manufacturing. Complete turnkey construction included delivery, set-up, fire alarm, fire sprinkler, site and building water, sewer and electric, sidewalks, gutters, awnings, decks, steps and ramps, and building foundations. An ECHO DCL Superintendent was present from Start to Finish.