Modular Medical Building
ECHO DCL completed the design and construction of three modular embedded health clinics for a total of 14,805 square feet. This facility is being used as a waiting room so patients do not have to wait in the exterior extremities.
Modular Construction: Scope of Work
Scope of work included design, engineering, and manufacturing. Complete turnkey construction included delivery, set-up, fire alarm, fire sprinkler system to meet NFPA 72, interior and exterior building communications, site and building water, fire water, sewer and electric, awnings, decks, steps and ramps, sidewalks and parking lots, automatic door openers, water barriers. ECHO DCL was on-site from mobilization to the completion of all work. An ECHO DCL Superintendent was present from Start to Finish.
Customer Name: Fort Drum Embedded Health Clinic
Address: Guthrie Health Clinic
Project Name: Fort Drum EBH
Contract Number: W912DY-12-C-0016
Prime Contractor: ECHO DCL, Inc.
Contract Type: FFP
1. Contract Date: September 30, 2012
2. Mobilization Date: April 8, 2013
3. Completion Date: August 21, 2013
4. Location: Fort Drum, NY