Fort Polk Modular PT/OT Clinic

By November 9, 2011Healthcare, Project Profiles

Customer Name:
John J. Kirlin Special Projects
Name/Title:
Chris Phillips – Quality Assurance
Address:
1585 3rd Street
Fort Polk, LA 71459
 
Project Name:
Modular PT/OT Clinic
Contract Number:
77014-12
Prime Contractor:
Icon Construction, Inc.
Contract Type:
FFP
1. Contract Date:
February 14, 2011
2. Mobilization Date:
May 31, 2011
3. Completion Date:
June 8, 2011
5. Location:
Fort Polk, LA

Icon completed the design and construction of one modular PT/OT Facility for a total of 11,045 square feet.  Scope of work included design, engineering, and manufacturing.  Complete turnkey construction included delivery, set-up, fire alarm/mass notification, nurse call, fire sprinkler, building communications, building water, sewer and electric, gutters, downspouts, awnings, decks, steps and ramps. An Icon Superintendent was present for 42 days from Start to Finish.