Customer Name:
|
U.S. Coast Guard MSU |
---|---|
Name/Title:
|
Mary Sennholtz |
Address:
|
2901 Turtle Creek Dr |
Suite 206 | |
Texas 77640 | |
Project Name:
|
Port Arthur Office Facility |
Contract Number:
|
GS-07F-0013U |
Prime Contractor:
|
ECHO DCL, Inc. |
Contract Type:
|
FFP |
1. Contract Date:
|
November 3, 2008 |
2. Mobilization Date:
|
November 10, 2008 |
3. Completion Date:
|
December 1, 2008 |
5. Location:
|
Port Arthur, Texas |
Portable Office Facility
![Portable Office Facility](http://icon-construction.com/wp-content/uploads/2012/08/DSC_0015-Medium-300x200.jpg)
ECHO DCL delivered the complete design and construction of one 2,090 square foot modular office facility. Scope of work included design, engineer, and manufacturing. Complete turnkey construction included delivery, set-up, steps, landings and handrails. An ECHO DCL Superintendent was present from Start to Finish. Project was completed within 15 days.